Program evaluation and review technique (PERT)
PERT is a time-event network analysis system in which various
events in a program or project are identified with a planned time established
for each. These events arc placed in a network showing the relationship of each
event to the other events.
This example illustrates the basic nature of PERT. Each circle of
the chart represents an event a supporting plan whose completion can be
measured at a given time. The circles are numbered in the order in which the
events occur. Each arrow represents an activity-the time consuming clement of a
program, the effort that must be made between events. "Activity
time", represented by the numbers beside the arrows, is the elapsed time
required to accomplish an event.
It is to
be remembered that an accurate estimate of time is difficult. When several
estimates arc made, they are usually averaged, with special weight given to the
most likely estimate; a single estimate is then used for calculations.
The next step is
to compute the Critical Path, that is, the sequence of events which takes the
longest time and which has zero (or the leas() slack time. In Figure 15.2. the
critical path comprises events 1-34-8-9-13. Over this path, the activity time
for this sequence of events is 131.6 weeks. If promised delivery is in 135
weeks, even this critical path will have been completed 3.4 weeks ahead of time.
Some of the other paths are almost as long as the critical path. For example,
the path 1-2-9-13 is 129:4
weeks. This is not unusual in PERT charts, and it is customary to
identify several critical paths in order of importance. Although the critical
path has a way of changing as key events arc delayed in other parts of the
program, identifying it at the start makes possible the close monitoring of
this particular sequence of events to ensure that the total program is on
schedule. A PERT analysis, involving large numbers of events, is usually
handled with computers.
No comments:
Post a Comment